September 2026 Capital Bond Program Update
Posted Date: 10/21/26 (10:42 AM)
Redmond School District 2024 Capital Bond Program: September 2026 Update
The Redmond School District’s 2024 Capital Bond Program continues to improve learning spaces and school facilities across the district. In September, most summer projects were finished, and all contractors were off site by the start of school. Remaining HVAC testing is expected to finish in mid-October. Current work is focused on Tumalo Community School and Redmond High School.
Program Administration and Local Vendors
Local contractors received 81.5% of awards: $66,654,097 of $81,766,063. In September, the program processed 5 contracts, 1 amendment, 6 change orders, and 68 invoices. To date, there are 114 design contracts totaling $9,910,916 and 45 construction contracts totaling $73,410,347.
Project Updates
• Athletic fields and turf: Summer 2025 projects at Redmond High, Ridgeview High, Elton Gregory Middle School, and Obsidian Middle School are 100% complete and in the warranty period through 10/02/26. New varsity turf fields are progressing at Redmond High and Ridgeview High.
• Tennis courts: Surfacing, perimeter fencing, and site work are complete. Flood and infiltration testing and the design team’s punch walk are done. The contractor is addressing punch items in October; construction is 90% complete.
• Hugh Hartman roof: Coping installation at steep-slope areas is complete. Work on low-slope sections continues as weather allows. The project is 95% complete, with punch walks and the manufacturer’s final visit next.
• Obsidian Middle School modernization: Ceilings, flooring, lighting, and restrooms were substantially complete September 1, 2026. Closeout, lighting controls commissioning, and punch-list work are underway.
• Redmond High School modernization: Construction is 20% complete and scheduled through 08/31/27. The Commons and Art classrooms were released after passing inspections, and the Auto Shop was occupied at the start of school. The Agriculture and Wrestling additions and CTE wing are progressing. Parking lot lights are energized, and accessible stalls and ramps are complete. The Modular Village is installed and turned over to help students remain on campus. East roof replacement and Phase 4 containment are coming.
• Sage and Terrebonne cooling retrofits: The work is 95% complete. Hydronic systems have been treated, chiller startup is underway, and testing and balancing are next. Chiller testing depends on warm weather.
• Tumalo Community School addition: The addition and renovation are 40% complete and scheduled through 08/15/27. Cafeteria/kitchen and classroom/science additions have moved from slab-on-grade to structural framing, and courtyard turf is installed. The new junior high wing is targeted for the 2027-28 school year, with four new instructional spaces: 6th, 7th, and 8th grade classrooms and a science room.
Financial Snapshot
Total revenue received is $109,431,511. The total project cost revised budget is $105,414,823. As of 9/30/26, $40,551,102 has been paid.
For questions, contact Chad Franke, Program Manager, at chad.franke@hmkco.org or 971.304.0710.