August 2026 Capital Bond Program Update

Posted Date: 09/22/26 (03:13 PM)



Redmond School District 2024 Capital Bond Program end of month report for August 2026, featuring a landscape view with mountains in the background.Click the image to view the full report

Capital Bond Program Update Summary – August 2026
Executive Overview
Redmond School District's 2024 Capital Bond Program continued significant progress in August 2026, with multiple projects completing or nearing completion before the start of the school year. The program maintains strong local participation with 81.5% of contracts ($66.7M of $81.8M) awarded to Central Oregon contractors and vendors.
Financial Status
  • Total Program Budget: $111,632,524
  • Allocated to Date: $104,693,471
  • Unallocated Balance: $6,939,053
  • Paid to Date (as of 6/31/26): $18,983,770
August Activity
  • 10 contracts established
  • 2 amendments processed
  • 11 change orders completed
  • 90 invoices processed
Project Highlights by Status
Completed/Substantially Complete
Obsidian Middle School Modernization (76% complete)
  • Major interior improvements completed: new lighting, ACT ceilings (43,662 sq ft), flooring, restroom renovations
  • Classrooms ready for teachers returning August 31
  • Substantial completion scheduled September 1
  • Budget: $2.2M revised
Summer 2025 Track & Turf Projects (100% complete)
  • All four schools (RHS, RVHS, EGMS, OMS) completed
  • Currently in warranty period (90% complete)
Active Construction
Redmond High School Modernization (15% complete)
  • Major milestone: Modular Village installed and operational
  • Environmental abatement progressing (Art, Admin, Commons, CTE wing, Wrestling)
  • Agriculture addition: CMU construction advancing
  • Roof replacement ongoing with manufacturer coordination
  • Budget: $65.8M revised (largest project)
  • Completion: August 2027
Tumalo Community School Addition (11% complete)
  • Foundation work advancing on cafeteria/kitchen and classroom/science additions
  • Summer renovations completed; classrooms ready August 31
  • Stem wall concrete placement completed
  • Budget: $13.5M revised
  • Completion: August 2027
Summer 2026 Tennis Courts (RVHS) (75% complete)
  • Concrete curbs and court foundations progressing
  • Awaiting infiltration testing before surfacing
  • Budget: Included in athletic fields
Hugh Hartman Elementary Roofing (75% complete)
  • Steep-slope asphalt roofing replacement completed
  • Low-slope roof system installation underway with manufacturer coordination
  • Weather-dependent completion timeline
  • Budget: $2.1M revised
Sage Elementary Cooling Retrofit (80% complete)
  • Exterior CMU chiller enclosure completed
  • Mechanical piping installation throughout building complete
  • Chiller startup scheduled pending suitable outdoor temperatures
  • Budget: $2.2M revised
Terrebonne Community School Cooling Retrofit (75% complete)
  • CMU chiller enclosure completed
  • New mechanical piping installed
  • Rooftop equipment setting and chiller startup scheduled
  • Budget: $2.1M revised
Key Challenges & Solutions
  1. Weather Dependencies: Low-slope roofing and HVAC startup require specific temperature conditions—teams monitoring forecasts and prioritizing work during suitable windows
  2. RHS Extended Closure Opportunity: School closure presents chance to accelerate work beyond original scope—requires intensive coordination for re-sequencing
  3. Environmental Coordination: Daily onsite presence by G2 Consultants ensuring safe abatement and trade access at RHS
  4. Testing Delays: Tennis court infiltration testing dependent on viewing port installation—team maintaining close coordination to minimize schedule impacts
Community Engagement
Active social media presence highlighting:
  • Construction progress across all sites
  • Student and family engagement activities
  • Contractor partnerships and milestones
  • Project-related campus tours